BUILDING SITE SURVEY AND SET OUT
Two Peg test | Grid levels | Volume calculation | Rectangular base method |
Triangular base method | MS-Excel Volume calculation | Contour lines | Assignment |
Two Peg Test All instruments are subject to errors. The checking of the instrument (level) is therefore important. The main error is where the line of sight is not parallel to the horizontal line of collimation. In this case your levels will not be correct. A test for checking the level is known as the two peg test. This test determines the amount of error and if an error occurs notify the technician (the level must be serviced).
Figure 1
- Establish 2 points approximately 50 metres apart on level ground as shown below. Set the level half way between the 2 points.
- Take the 2 staff readings. In our example an error will exists (line of sight does not coincide with line of collimation).
Figure 2
- Move the level as close as possible to one of the peg. (In the case above 'Peg A').
Take the 2 staff readings again. - If the difference in height is the same the level is okay. If not, as shown in the example above, the instrument needs to be serviced.
[ top of page ]
Grid leveling is used for site investigation, for drawing contour lines and for the easy calculation of volumes.
The opposite figure shows a typical survey of a site using grid point levels. The area of the site is divided into a number of squares 5×5 metres (triangles or rectangles can also be used) and levels are taken at corner points. The grid levels enable us to calculate the volume of material above or below a certain reduced level (RL) and to draw contour lines. In the example one 12.9 m contour line is shown.Figure 3
The lowest level of the site is RL=10.000 m and the highest is RL=15.831 m.[ top of page ]
Figure 4
The two grid elements F and R are truncated prism of which the area is 5×5 metres and the height of the prisms is to be the mean of the four corner heights. Therefore for the volume of the prism F is:
[ top of page ]
As can be seen prism F is surrounded by other prisms and each corner must be counted four times. The corners of the prism R on the other hand must be counted one (corner), two (at the boundaries) and four (internal corner) as shown in Figure 4.
If you consider the whole lot (20 m x 20 m) and take an average of all the grid points (25 RL's) the volume quantity would be incorrect. Instead of calculate 16 single prism we could record a total of 64 points (RL's) with the number occurring at each intersecting grid point as shown in Figure4. Each corner RL occurs 1 time, all other RL's on the boundary 2 times and all internal RL's 4 times.
Then the RL's need to be multiplied by the times occurring on the grid points. Both columns added up and the sum of the levels is then divided by the sum of the points as shown in Table 2.A MS-Excel program can quickly do the work for you. See below for additional information and a complete calculation example is shown in Table 2.
Figure 5 | Table 1 |
top of page
Triangular Base Method This is even a more accurate calculation method. Triangular elements can better define the surface because three levels define a plane. (A desk with three legs cannot wobble which happens with four leg tables.) In this method the volume is calculated of prisms with triangular bases. The calculation process is similar to the above method but with a higher number occurring at each intersecting grid point. Each corner RL occurs 1 or 2 times, all other RL's on the boundary 3 times and all internal RL's 6 times with a total of 96 occurrences.
Figure 6
[ top of page ]
The work of getting the average of the spot levels can be simplified by the use of a suitable table as illustrated below:
Step 1Sum up the column 5 & 6 and find the mean height (MH) by dividing the sum of the levels by the sum of the number of common points.
Step 2MH = 824.999/64 = 12.891
Find the difference between the mean height (MH) and the proposed finish ground level (FGL).
a) the difference can be positive(+ve) or negative (-ve).
b) if the mean height is greater (+ve) than the finish ground level (FGL) then it is a cut.
c) if the mean height is smaller (-ve) than the finish ground level(FGL) then it is a fill .
MH < FGL = FILL
MH > FGL = CUT
MH = FGL then CUT = FILL
Step 3
Multiply the difference (from Step 2) with the area of the lot to find the required volume.
In the isometric view the finish ground level is: FGL=12.900
Therefore the mean height from Step 2 minus the given RL MH12.891-12.900=0.009
[ top of page ]
Contour lines show the vertical dimension (the third dimension) of the ground on site plans. The vertical distance separating contour lines gives an indication of the steepness of the slopes. A few simple rules for contour lines will be helpful in interpreting the vertical dimension of a building site.
In general gentle slopes are represented by widely spaced contour lines.Steep slopes are represented by closely spaced contour lines.
The contour lines shown in Figure 7 spacing at 500 mm interval.
Figure 7
There are two methods to plot contour lines: a) by estimation b) by calculationa) is the quickest method of plotting the contours. Estimate by visual inspection the position of a contour between two adjacent spot levels.
b) is more accurate if the ground between the RL's is nearly straight. Similar triangle rule is then used to calculate the contour line.Method a)
Contours lines are at 500 mm interval, that means there are two contour lines between grid point 21 (RL 10.541) and grid point 16 (RL 11.687) the 11.000 and 11.500 respectively. The distance between the two RL's is 5 metres. By estimation the 11.000 contour line would be approx. 0.4 × 5 m 2.000 m from RL 10.541 and the 11.500 contour line would be close to RL 11.687
We use similar triangles to to find the intersection of the contour lines on the level grid. For example the difference between RL 10.541 (grid point 21) and RL 11.687 (grid point 16) is 1.146 metres. The difference between contour line 11.000 and RL 10.541 is 0.459. This figure will be used to calculate the intersection of the 11.000 m contour line. As the increment for contour lines is 0.500m we add 0.500+0.459 = 0.959 to find the 11.500 contour line intersection. 0.459 and 0.959 is now used to find the distance d1 for the 11.000 and d2 for the 11.500 contour lines. This principle of calculation is show below and should be used for all your exercises and assessments that involves drawing contour lines.
Using similar triangles:
Using the above equation the actual calculation for the contour lines 11.000 m and 11.500 m is:
Sometimes you know the distance for a specific point on a grid system and want to know the reduced levels (RL's) that belongs to it. In this case use the formula to the right to find the value that need to be added to the reduced level (RL). | RL-Calculation |
adding 0.459 to RL 10.541 equals to RL 11.000 m, which is also the 11.000 m contour line height. |
[ top of page ]
The opposite figure shows a building site. The lot is 50 × 40 metres and has spot levels at 10×10 metre grid points as indicated. 1) For this site draw all contour lines at 1 metre interval. The distance on the grid lines must be calculated using the formula for similar triangles. 2) Find the reduced level to establish a finish ground level (FGL) by utilising the cut and fill method (cut equals fill) 3) How much soil is required if the RL of the building pad (FGL) is to be 16.300. Calculate the volume. If submitted to the lecturer the correct answers will be emailed to the student
Figure 8